Pinellas Drivers Stuck on US 19 Until 2030 as Officials Trade Blame

·

Construction on a major stretch of U.S. 19 through Pinellas County will continue until 2030, more than two years behind schedule, as county officials and the private contractor point fingers over who is responsible for the delays.

The $242.7 million Florida Department of Transportation project runs from State Road 580 in Clearwater to north of County Road 95 near Curlew Road in Palm Harbor. It adds interchanges, overpasses, and frontage roads intended to improve traffic flow on a corridor that carried an average of 105,000 vehicles per day in 2024. Johnson Brothers Corporation received the contract in 2022, and work began in spring 2023. FDOT now lists a 2030 completion date. Frontage roads may open earlier, in 2028.

County utility work has become a primary bottleneck. Crews must relocate roughly one mile of a major water main that feeds the county’s system, and officials also want to fix a leaking valve near Evans Road while crews are on site. Road construction in the affected area cannot proceed until that utility work is finished. Negotiations over scope and cost have dragged on for months.

On November 17, Pinellas County commissioners voted 4-3 to increase an existing utility repair contract with QRC Inc. by $10 million, with about $4.5 million of that amount directed at the U.S. 19-related water main and valve work. County staff argued that the move would give them greater control and speed progress. They cited concerns about the quality and pace of utility work already performed under the Johnson Brothers contract. Utilities Director Jeremy Waugh told commissioners the overall highway project was already more than 800 days behind schedule and that further delays could expose the county to claims of roughly $230,000 per week.

Johnson Brothers opposed the change. Company representative James Charles told commissioners that design problems and slow responses from the county’s engineer had hampered the job. He said the contractor raised concerns about the water main’s pipe restraint system in March 2025, but revised plans did not arrive for more than five months, with additional revisions following in January 2026. A similar six-month lag occurred on a drainage structure issue. The company has identified six major delay drivers and put associated costs at $20.7 million. Charles argued that the county could work with FDOT to let Johnson Brothers handle the work under its existing contract and urged a clear price comparison. He noted that Johnson Brothers had priced revised Evans Road work at about $2.64 million and questioned how that compared with the county’s $4.5 million allocation.

Commissioners considered postponing the vote for more review, but staff warned that waiting another month risked additional claims. Commissioner Kathleen Peters moved for approval, and Commissioner Rene Flowers seconded. The close vote reflected lingering questions about cost, control, and whether bringing in a second contractor would actually accelerate the project or simply add another layer of coordination.

For nearby residents, the timeline feels longer still. In the Curlew City neighborhood east of U.S. 19, Grace O’Brien has dealt with congestion entering and leaving her street for more than three years. She said residential streets have become alternate routes for drivers and routes for heavy construction equipment. “It’s been going on for too long,” she said. “They don’t look like they’re anywhere near being completed.” She supports the eventual overpass but questions how long the disruption will continue and how little the work appears to account for the surrounding community.

Businesses along the corridor continue operating amid lane shifts and changing traffic patterns. The project’s stated goal remains better long-term traffic flow and preserved access, yet utility conflicts, plan revisions, and agency disputes have already extended the construction window by years and raised the prospect of further cost claims passed from the contractor through FDOT to the county.

Drivers and taxpayers now face at least four more years of the current conditions. Whether the latest $4.5 million commitment and the shift to QRC will actually shorten that timeline, or simply continue the pattern of added expense without clear accountability, remains the open question.